top of page

Titan Group

Overview

​

We were approached by Titan Group to look at a project in Stratford which was midway through completion. The site consisted of 180 apartments which needed the MBUS heat meters reinstated and network brought into operation with a local head end.

Titan were experiencing many issues with their network and were unable to rectify the problems faced.

​

Background

​

Upon inspection of the site the following issues were noticed and needed to be actioned:

​

  • Batteries on meters were very low or failing

  • The MBUS needed re-caballing to allow data to transmit back to the master

  • The hardware addressing of the meters themselves would not allow data to freely transmit and also caused network crashes

  • Some meters or probes needed reinstallation to allow the meter to operate

  • Some Meters were not sealed

  • No head end in place and needed to be installed and set up

​

Solution

​

​

  • First of all we needed to put a plan in place to logically address the problems with the meters and network which had to work in the following order:

  • Batteries needed to be replaced

  • The addressing needed to be reinstated according to our MBUS re-addressing plan

  • Probes and flow sections need to be checked and rectified

  • Meters then needed to be checked commissioned and sealed

  • The master unit needed to be fitted into the basement to allow reading of the meters

  • Set up of head end on local PC (this is generally not advised due to the potential of data loss) but was insisted on by the client

  • Commissioning, handover and training of the system

​

​

Cost Benefits

​

​The client now has the means to bill all the tenants within the development to accumulate a revenue in excess of £80,000 per annum with a reliable and fault free system.​

​

​

athena.jpg

MORE CASE STUDIES

bottom of page